What's the difference between G98 and G99?

G98 is connect and notify. G99 is apply first and wait for the network operator to say yes. Which one you're on comes down to the total inverter capacity on the property.

G98 is for systems where everything that can feed power out, solar inverter and battery inverter added together, comes to 16A per phase or less. On a single-phase house that's 3.68kW, on three-phase it's 11.04kW. It's the inverter rating that counts, so a panel array a bit bigger than 3.68kW on a 3.68kW inverter still sits under G98. We fit it, commission it, then tell the network operator no later than 28 days after.

Go over 16A per phase in total and it's G99. That catches a lot of battery jobs. Add a separate 5kW battery inverter to an existing 3.68kW solar system and you're well past the limit, even though neither one is big on its own. Under G99 nothing gets connected till the network operator has assessed it.

For smaller domestic systems there's a quicker G99 route. If the inverters are type tested and an export limitation scheme (G100) caps what the house can send to the grid, the network operator should come back within 10 working days. If they decide the local network needs a proper look, it moves to their standard application and you wait for that to finish. Bigger systems go straight to the standard application.

In Scotland the network operator is SSEN in the north, or SP Energy Networks across central and southern Scotland. You don't need to deal with either. We work out which route your system needs at the survey and put in the G98 notification or G99 application as part of the job, so you know before we start if there's a wait.